What a Difference Two
Years Have Made!
Rod and Sherry Boyd
What a Difference a Year Makes was our
report from last Christmas a year ago on construction
progress of the Latin America Resource & Training Center in
Panama. This Christmas, we look back at what God has done in
2017 and declare, what a difference two years have made! We
are living the fulfillment of a twelve year-old dream!
A year ago, we were celebrating the completion of the
structure of Building One. On February 20th, we moved our
offices to the second floor and by the end of July, all
finish work was complete! We also stepped out in faith to
begin construction of Building Two and believed God that the
10 guestrooms on the first floor would be completed by July
31st.
Once again, God used two teams - Portland Christian Center
(OR) and Calvary Christian Assembly (Seattle, WA) - and many
generous people and ministries to provide needed funding to
be able to complete this work and more! Thirty-two students
and teachers moved into those rooms for study four weeks in
August.
Thanks to the excellent work of MAPS Construction Teams from
Grove Church (Marysville, WA) and Eastridge Church
(Issaquah, WA) in October and November, nearly all of the
perimeter block work is complete on the second floor of
Building Two. Even before these
two teams arrived, the Lord miraculously provided funding to
purchase materials and install the roof, and to build the
stairwell for Building Two. When finished, the second floor
will add 13 new guestrooms, allowing us to house nearly 100
leaders, pastors and teachers.
Work is currently underway to bring the first-floor kitchen,
pantry, laundry and storage rooms to construction finish
(tile, ceiling, electrical, paint, lighting, plumbing,
windows and doors). The Eastridge Church team generously
provided funds for a commercial washer and dryer. We are
believing God for a women’s group to “adopt” the equipping
of the commercial kitchen!
What a different 2 years have made! From 0% the end of 2015
to 25% the end of 2016, we have now completed more than 50%
of the LARTC construction! We continue to see God’s
miraculous hand at work through your generosity and His
stretching provision for maximum value. Below is a summary
of the progress of our five construction phases.
1 -
Training/Admin/Production, 9,200 sq ft (2016-17)
100%
COMPLETE!
2 -
Housing/Kitchen, 15,200 sq ft (2017-18)
65% COMPLETE!
3 -
Atrium: Reception/Auditorium/Dining, 5,700 sq ft (2018-19)
4 -
Training/Admin Addition, 5,200 sq ft (2019-20)
5 -
Staff Housing, 4,200 sq ft (2020-21)
Please pray for us and the Center in 2018: Faith to believe
for miraculous provision, wisdom in how it is used, and
strength and anointing to serve as God continues to open
doors for ministry. We will be working on two fronts in 2018
as funds permit. First, we hope to finish the 13 guestrooms
on the second floor. Second, we hope to begin construction
of the Phase Three Atrium building!
Even now, with the new facilities we are better able to
empower leaders, train teachers and produce resources. We
need your help to finish what we’ve started! In addition to
praying, as God prospers you, please include the LARTC
Project in your year-end giving to the address above.
Together we are raising up Christian leaders in Panama and
throughout Latin America to train harvest workers who will
go to the ends of the earth!
|